Westwood Lake Park Amenity Improvements
Consultation has concluded
Get Excited! Improvements are coming to Westwood Lake Park!
The next phase of improvements at Westwood Lake is beginning September 3. Based on public feedback, look for these improved amenities creating a high quality recreation space:
• Increased accessibility
• Shade trees
• Improved recreation space
• Expanded beach area
• Updated washroom/changeroom facility
• Enhanced pedestrian and bike connections
• Addition of seating and tables
• Green stormwater infrastructure
Please pardon the mess during construction. For your safety, follow contractor’s safety and directional information while using the park.
Note that the first entrance to the parking lot will beContinue reading
Get Excited! Improvements are coming to Westwood Lake Park!
The next phase of improvements at Westwood Lake is beginning September 3. Based on public feedback, look for these improved amenities creating a high quality recreation space:
• Increased accessibility
• Shade trees
• Improved recreation space
• Expanded beach area
• Updated washroom/changeroom facility
• Enhanced pedestrian and bike connections
• Addition of seating and tables
• Green stormwater infrastructure
Please pardon the mess during construction. For your safety, follow contractor’s safety and directional information while using the park.
Note that the first entrance to the parking lot will be the only one available and that the boat launch is within the construction zone and will not be available until the spring.
Vehicle access changes and interim pop-up parkette at Westwood Lake Park
The City is implementing access changes to Westwood Lake Park in advance of park improvements which are planned for construction this fall and winter.
Starting late June, the third (and final) gate access into the park at the end of Westwood Road will be accessible to boat launch traffic only.
All other vehicle traffic wishing to enter the park must now do so through the new parking lot on Westwood Road. The gravel parking lot close to second beach is also accessible through the new parking lot.
Park users are asked to follow on-site signage and flaggers will be on-site this week and through the Canada Day long weekend to help parks users get used to the change.
This change is being made along with minor beach maintenance including the removal of the old metal railing at the rear of the beach, topping up of beach sand and the installation of a temporary pop-up parkette in what was the parking lot just behind first beach.
The pop-up parkette is temporary for this summer and is located on portions of the park that will become beach and recreational open space in the next project phase. The pop-up parkette features temporary seating, recycled artificial turf, and sand. The area may also be programed with various activities over the summer to promote public use of this new pedestrian space.
Phase 2 construction will include permanent beach expansion at First beach, amenity improvements and inclusive washrooms, is expected to begin Fall 2024.
______________________________________________
Westwood Lake Park, one of the busiest and most popular places to visit in Nanaimo, is about to undergo a variety of improvements. Phase 1 will begin this year and includes improvements to the park entrance, including:
- enhanced natural green spaces
- improved parking (moving some current spots to lessen environmental impact, using permeable and impermeable surfacing and adding 36 additional spots and 4 additional accessible parking stalls)
- better parking lot circulation flow and safety features
- planting of additional native trees and shrubs
- integration of stormwater management areas and rain gardens to capture and filter rainwater
- mobility improvements along Westwood Road for both pedestrians and cyclists
Through a variety of public engagement opportunities in 2020 and 2021, including the ReImagine Nanaimo process, it was evident that the public is wanting improvements to Westwood Lake Park to better meet the needs of the community. It is a prime destination for swimming, walking, running, paddling, biking, fishing, nature appreciation and public events.
AMENITY IMPROVEMENT IDEAS
The initial draft improvement options focus on the area formerly occupied by the Caretaker House, as well as the main entrance off Westwood Road, first parking lot, and First Beach. Elements in the site plans are interchangeable and are ideas to see what the public would like to see.
The initial draft improvement concepts include the following improvement ideas:
- Expansion and new recreational improvements at First Beach
- Improved universal access features, including washroom (new or renovated), trails, and beach and water access
- Increased parking capacity, including additional accessible parking stalls
- Improved traffic navigation, including improved entranceways and exits
- Improved pedestrian circulation and safety improvements
- Site furnishings that can be enjoyed by all users
- Additional picnic and special event areas
- New playground
- Improved flow for boat launching
- Improvements to trail navigation at entrance area, including 3m accessible trail network
- Storm water management considerations to capture and filter storm water, including sustainable paving options to improve site ecology
- Additional shade trees
- Enhancement of natural areas through new plantings in excess of any removals and vegetation retention (a buffer between the park and the houses on Leighton Place will also be included)
- Bike wash facility
- Consideration for lifeguarding facilities and emergency access
SITE PLAN 1: FIRST IDEAS (see image below)
All of these park improvement ideas are interchangeable and are intended to spark discussion.
Key Features:
- 75 additional standard parking stalls (134 in total)
- 2 additional accessible parking stalls (6 in total)
- 840 square metres of additional beach/picnic area
- new playground
- new 3 metre wide multi-use trail
- renovated washroom/lifeguard station
- non-motorized boat launch to remain
- new emergency access
- new trees to be planted in excess of trees removed
- stormwater management feature to capture and filter rainwater
- universally accessible features, including beach and water access that would be wheelchair accessible
- Existing accessible float
- Existing washroom/lifeguard station to be renovated and made universally accessible
- Existing vendor area and power kiosk
- New playground (design/equipment to be determined)
- Additional beach/picnic area
- Accessible parking stalls
- Asphalt or alternative hard surfacing drive aisle and parking area
- Vegetated swale
- Bike wash facility
- Multi-use trail
- Vegetated buffer
- Accessible beach access
- Boat launch
SITE PLAN 2: MORE IDEAS (see image below)
All of these park improvement ideas are interchangeable and are intended to spark discussion.
Key Features:
- 55 additional standard parking stalls (114 in total)
- 2 additional accessible parking stalls (6 in total)
- gravel parking stalls reduce impervious area
- 840 square metres of additional beach area
- new accessible washroom/lifeguard station
- new picnic area
- new 3 metre wide multi-use trail
- boat launch to be relocated to second parking lot
- new emergency access
- new trees to be planted in excess of trees removed
- new playground at second beach area
- stormwater management feature to capture and filter rainwater
- Existing accessible float
- Future special event area
- Existing vendor area and power kiosk
- New picnic area
- New accessible washroom / lifeguard station
- Additional beach area
- Accessible parking stalls
- Permeable hard surfacing
- Vegetated swale
- Reinforced gravel parking stalls
- Bike wash facility
- Multi-use trail
- Vegetated buffer
EXAMPLES OF IMPROVEMENT IDEAS FROM OTHER PUBLIC SPACES THAT COULD BE IMPLEMENTED AT WESTWOOD LAKE PARK
BACKGROUND
Westwood Lake Park is a jewel in the City of Nanaimo’s park system. Highly used by the community, and it is a favourite with visitors, this park sees heavy use all year round. Over 800 people enjoy the main trail loop every day. The beaches are a popular destination in the summer and there are many options to fish and paddle on the lake. In the last few years, there has been a steady increase in mountain biking and use of the park to access a greater trail network. The area is also a popular venue for events such as triathlons and fundraising runs.
Westwood Lake is a fabricated lake created when Darough Creek was dammed for hydroelectric production in the early 1900s by the regional power network. The hydroelectric plant was abandoned in the 1950s, and the City of Nanaimo purchased the land and dedicated it park in 1957.
Improving and increasing access to waterfront areas has been a community priority identified in Parks, Recreation and Culture Master Plans since 1994. Acquisition of land adjacent to Westwood Lake Park has also been a focus, and several additional park parcels have been acquired over the years by purchase and through the development process.
REIMAGINE NANAIMO
Community feedback was collected through Phase 1 of REIMAGINE Nanaimo regarding a variety of community issues. Westwood Lake Park was specifically brought up through engagement with several community organizations, including the Westwood Neighbourhood Association (Friends of Westwood), immediate park neighbours, and various user groups with interest in the park and surrounding areas. A short summary of the input includes:
- Maintaining the park's natural area as much as possible
- Addressing overuse concerns, including issues with trail maintenance, trail widths, parking areas, and parking overflow
- Continuing to acquire additional land parcels to increase the park size
- Improving traffic flow, conflicts between multiple park users, and emergency access
- Considering structures for events and group park use such as a picnic shelter
- Adding park amenities, including a new playground, picnic facilities, activities like sand volleyball, and areas with shade etc.
- Adding site furnishings, including seating, picnic tables, ping pong tables, etc.
- Addressing universal accessibility concerns – washrooms, parking, access to water; adaptive single track trails, boat launch, fishing pier, signage and trail condition information
- Expanding single track trail networks for mountain biking and wilderness recreation
- Improving amenities and access to the lake for recreational fishing
Phase 2 of the REIMAGINE Nanaimo process is currently underway. REIMAGINE Nanaimo is focused on achieving integrated community goals and this project, when implemented, can showcase integrated community goals such as being Healthy, Connected, Enabled, Empowered and Ecological.
The Westwood Lake Park Amenity Improvement survey will be open through Thanksgiving for input (closes on October 31). In addition to the public survey, engagement activities will include a number of stakeholder meetings, including park neighbours and accessibility advocates, online feedback through GetinvolvedNanaimo.ca, and in person engagement at the park and through committees of Nanaimo City Council.
WESTWOOD LAKE PARKING AND ACCESS
There are currently three areas for cars to park and provide access to Westwood Lake Park. Future active transportation links and transit will also be explored to help provide public access without vehicles. The three existing parking locations are depicted below.
WESTWOOD LAKE ZONING
Most of Westwood Lake Park is zoned PRC-1 Nature Park with a focus on natural spaces. The beach areas are zoned PRC-2 to allow for a variety of recreation and cultural amenities.
TREE IMPACT AND REPLANTING
To accommodate additional parking, some trees would need to be removed. A similar number would be impacted by both conceptual parking layouts.
- Approximate number of significant trees* to be removed: 4
- Approximate number of non-significant* trees to be removed: 36
*as defined in City of Nanaimo Bylaw 7126
To offset these impacts, over 40 replacement trees would be planted throughout Westwood Lake Park to enhance and offset any tree canopy loss. Like anyone cutting down trees in our community, the City of Nanaimo would apply for tree removal permits as required in Bylaw 7126 and exceed the replacement requirements. Shade trees and other buffering vegetation would also be planted to restore and enhance the entrance and impacted area near First Beach.
In addition, a Tree Stand Management Plan for the entire park was completed in Summer 2021. A biophysical inventory of the entire park is also being considered to better evaluate park natural features and tree impacts as park use grows and climates shift to help protect the natural character of the PRC-1 natural park.
Key Dates
-
October 31 2021
-
January 05 2023
-
January 09 2023
-
June 01 2023
-
July 03 2024
Important Links
Timeline of Development of Westwood Lake Park (First Beach and Westwood Road park entrance)
-
1860s
Westwood Lake Park Amenity Improvements has finished this stageW.J. Westwood purchased 265 hectares of land at the foot of Mt. Benson for farming.
-
1907
Westwood Lake Park Amenity Improvements has finished this stage80 hectares of the Westwood Farm and swampland were purchased by the Canadian Western Fuel and electric Company in 1907 (they owned lots of land along the Millstream River and downtown waterfront). The Canadian Western Fuel and Electric Company then constructed a dam in the early 1900s.The resulting reservoir is now called Westwood Lake (named after the Westwood Family who homesteaded the area). At that time, the lake provided a reserve water supply for Nanaimo’s Millstream River electric power station.
-
1957
Westwood Lake Park Amenity Improvements has finished this stageWestwood Lake and its forested surroundings were officially designated a park on January 27, 1957. Many community groups partnered with the City of Nanaimo to build park amenities, including the Nanaimo Legion who helped build First Beach for public recreation.
-
2006
Westwood Lake Park Amenity Improvements has finished this stageCity purchased acquired additional land off Westwood Road adjacent to the park, including a caretaker’s house in order to prepare for future parking lot expansion.Over the years, the City has continued to acquire properties adjacent to Westwood Lake to increase the park size/protected areas and also continued to build public amenities at the site.
-
2012
Westwood Lake Park Amenity Improvements has finished this stageCity of Nanaimo and the Nanaimo Mountain Bike Club partnered to develop single track mountain bike trails at Westwood Lake Park to meet growing community demand.
-
2020
Westwood Lake Park Amenity Improvements has finished this stageCaretaker house adjacent to First Beach was demolished to allow for future parking lot expansion.
-
2021
Westwood Lake Park Amenity Improvements is currently at this stageNanaimo City Council approved the testing of improvement ideas and amenities at Westwood Lake Park with the public.
-
2023 - Construction to Begin - Contract awarded
this is an upcoming stage for Westwood Lake Park Amenity ImprovementsThe contract has been awarded to Windley Contracting Ltd. Construction will begin in mid January and is expected to be complete in May 2023.
Photos
Documents
- Council Report Westwood Lake Park Amenity Improvements And Engagement Update.pdf (153 KB) (pdf)
- Attach B: Survey Comments - Westwood Lake Park (2.26 MB) (pdf)
- Attach C: Stakeholder Input - Westwood Lake Park (161 KB) (pdf)
- Attach D: Neighbourhood Meeting Notes - Westwood Lake Park (85.6 KB) (pdf)
- Attach e: Final Concept Plans - Westwood Lake Park (11.4 MB) (pdf)