The Public Works Yard Updates Project – Financing 101
Construction costs have escalated wildly in the past four years across Canada. While we wish we could go back in time and build this when costs were more affordable, we can at least move forward before they get higher. Here’s a look at the project, which involves borrowing up to $90 million:
Construction | $48,000,000 |
Project Delivery* | $14,000,000 |
Allowance for Inflation | $10,000,000 |
Contingency | $18,000,000 |
Maximum Borrowing | $90,000,000 |
* Project Delivery includes costs for design, insurance, third-party utilities (hydro, telephone), permitting, etc.
It’s worth noting that these potential amounts include allowances for cost overruns and inflation, and the City will only borrow what’s needed, when needed, and will only use the funds for this project. However, we can only ask once, so we need to ensure that the amount will be sufficient.
A large project like this doesn’t happen without an impact on property taxes, but if financing is approved by the public through the AAP, then the borrowing costs will be spread out over 20 years. If the full amount is borrowed, then once borrowing is complete, the average cost per household per year will be about $139 (about $18 per $100,000 of assessed value and an average Nanaimo home value of $783,808*).
*Rounded to the nearest dollar. Tax impact based on 2024 figures and a 20 year amortization of 4.58%.
Below is a more detailed project cost breakdown (see pdf for explanation of the chart below).
Cost Type | Item | Estimated Cost |
---|---|---|
Construction | Crew and Administration Building | $21,000,000 |
Fleet Maintenance Building | $16,000,000 | |
Storm water Treatment and Servicing | $3,500,000 | |
Site Servicing | $1,500,000 | |
Surface Works and Site Development | $1,500,000 | |
On-site Electrical Infrastructure | $1,500,000 | |
Relocate the Materials Storage Facilities | $1,500,000 | |
Road Improvements and Site Entrances | $1,000,000 | |
Site Security | $500,000 | |
Construction Sub-Total | $48,000,000 | |
Project Delivery | Professional Services (Design, Legal, Admin., Inspection, Etc.) |
$9,000,000 |
Furnishing, Fixtures, and Equipment (Inc. Fleet Maintenance Equipment) |
$2,000,000 |
|
Permitting and DCCs |
$1,500,000 |
|
Off-Site Work |
$525,000 |
|
Third Party Utilities |
$500,000 |
|
Insurance |
$400,000 |
|
Move Costs |
$75,000 |
|
Project Delivery Sub-Total |
$14,000,000 |
|
Inflation | Projected to May 2028 |
$10,000,000 |
Contingency | 25% (Class D) |
$18,000,000 |
Total Recommended Budget |
$90,000,000 |